Installation instructions
Installation instructions
For felt and batten roofs, start by fixing battens minimum size of 2" (50mm) by 1" (25mm) treated battens over underlay to the required gauge. The first course and eaves (starter) course should oversail the fascia by at least 1½" (38mm), so the first course batten should be placed approximately 7½" (190mm) centrally from the start of the roof (see diagram). A second batten should then be placed directly under the first course batten to accommodate the eaves or starter course (made from a cut ¾-slate).
TapcoSlate - Classic Tile - Roofing tile
TapcoSlate - Classic Ridge To Hip Junction - Pitched roof ridge-to-hip junction
TapcoSlate - Classic Ridge And Hip Cap - Pitched roof ridge and hip cap
TapcoSlate - Classic Ridge End Cap - Pitched roof ridge end cap
TapcoSlate Classic BBA Certificate
TapcoSlate Classic ETA Certificate
Protect Wunderlay Membrane Q Mark
Protect VP300 Membrane Certificate