OVERVIEW
Following a successful first phase in 2018, London Power Tunnels 2 (LPT2) is a project to ‘rewire’ south London. The six-year, £1bn scheme will comprise the construction of 32.5km of 3m-diameter tunnels built deep below the road network between Wimbledon and Crayford to carry high voltage electricity cables.
A Hochtief-Murphy Joint Venture (HMJV) was awarded the contract in December 2019 to design and construct the tunnels & shafts and install the EHV (extra-high volume) cable brackets. The New Cross site is one of several in the overall scheme.