OVERVIEW

We were brought in by Middlesbrough Council to complete the roof refurbishment of Abingdon Primary School.


Systems in use


Overview


We had originally worked with Middlesbrough Council to complete Abingdon Primary School’s first phase of the roofing in 2015, and were asked to review the remaining flat roof areas to bring them in line with the previous phase.


Challenges


With this being a school, all works had to happen outside of school terms, so works began at the beginning of the summer holidays and had to be completed before the start of the September term. This on its own posed challenges to make sure that all roofing works were completed on time so as not to disrupt any of the children’s educations. Logistics were crucial, as was collaboration between Axter, NT Sweeting and Middlesbrough Council.


There was also the issue of combustible areas around the perimeter of the building with some cladding details and some windows that could not be detailed in a traditional torch on application.


Solutions


Working closely with Middlesbrough Council from the outset, we surveyed the roof area and ensured the new waterproofing and previously completed phase were compatible. We also liaised closely with NT Sweeting to make sure all products were available and delivered to site on time to avoid unnecessary delays to the roofing works.


Our Excel reinforced bitumen membrane system was specified for the main roof area; the membrane is manufactured with the unique Alpa polymeric binder, making it our most technologically advanced RBM system.


Axter’s Starcoat R cold applied liquid bitumen PU resin was used to detail combustible items picked up in our report, including interface to windows and cladding abutments in line with Safe2Torch guidelines, which eliminated all fire risk.




Products featured in this case study

View all products (18)
Excel Warm Roof Single Layer System - Concrete Roof Slab (In-situ/ Pre-cast) / Timber Roof Deck / Profiled Metal Deck

Excel Warm Roof Single Layer System - Concrete Roof Slab (In-situ/ Pre-cast) / Timber Roof Deck / Profiled Metal Deck

Excel® FM Warm Roof Flame Free Mechanically Fixed Single Layer System - Timber Roof Deck / Profile Metal Deck

Excel® FM Warm Roof Flame Free Mechanically Fixed Single Layer System - Timber Roof Deck / Profile Metal Deck

Excel® FM Warm Roof Mechanically Fixed Single Layer System - Timber Roof Deck/ Profiled Metal Deck

Excel® FM Warm Roof Mechanically Fixed Single Layer System - Timber Roof Deck/ Profiled Metal Deck

Excel® Warm Roof Multi Layer System - Concrete Roof Slab (In-situ/ Pre-cast) / Timber Roof Deck / Profiled Metal Deck

Excel® Warm Roof Multi Layer System - Concrete Roof Slab (In-situ/ Pre-cast) / Timber Roof Deck / Profiled Metal Deck

More inspiration from Axter Ltd

View inspiration
Bexley Park Sports & Social Club

Bexley Park Sports & Social Club

West End Gate, London

West End Gate, London

Escapade Silverstone

Escapade Silverstone

Desborough Library

Desborough Library

More inspiration from Reinforced bitumen membrane warm roof covering systems

View inspiration
Allenby Barracks

Allenby Barracks

Jesus College

Jesus College

Waverley Court

Waverley Court

Colchester County High School

Colchester County High School