NBS Source
I'm a manufacturer

Maldron Hotel Swimming Pool Renovation Tiles and Tanking | Precision Building Services

OVERVIEW

Job:

Maldron Hotel Swimming Pool

Renovation, Portlaoise, Co. Laois.


Smet Supported Partner:

Precision Building Services – Mark Pemberton


Products:

Sopro Rapidur® B5 Rapid Drying Screed Binder

Merlin Barrier Coat

Sopro RAM 3 (454) Renovation and Levelling Mortar

Sopro GD 749 Universal Floor and Wall Primer

Sopro DSF® 523 Tanking Membrane

Sopro PUK 503 PU Adhesive

Sopro VF HF 420 – VarioFlex® High Strength Flexible Tile Adhesive

Sopro’s No. 1 Flexible Tile Adhesive

Sopro FKM® XL 444 – Extra Light Weight Tile Adhesive

Sopro Sanitary Silicone

Sopro DE 014/015 Sealing Corners

Sopro FEP 508

Sopro DBF-638

Racofix 818


Description:

SMET supplied Smet Supported Partner, Precision Building Services (Mark Pemberton), for the renovation of the Maldron Hotel Swimming Pool, Portlaoise, Co. Laois.


A total area of Floor screed @ 140m² | Wall tiling @125m² | Floor tiling @ 140 m² was completed.


New floor installation with fast-track – rapid drying floor screed solution, using Sopro Rapidur® B5 Rapid Drying Screed Binder, a fast-setting screed which was laid to falls prior to waterproofing and tiling providing an early completion. 


German-made Rapidur® B5 Rapid Drying Screed Binder is a special polymer-modified binder for particularly economical ­production of high-strength, rapid-set cement screed – based on DIN 18560.


Rapidur® B5 is suitable for use on heated screeds, bonded screeds, unbonded screeds and floating screeds. This flooring solution is particularly useful for fast-track or tightly scheduled screed laying. The newly laid Rapidur® B5 screed floor is ready to receive floor covering after approx. 3 days – after achievement of moisture content ≤ 1.8 % CM. Sopro Rapidur® B5 is supplied in 25kg bags, with 40 bags per pallet.


Sopro Rapidur® B5 was installed directly on top of Merlin Barrier Coat wet on wet. The screed was ready for waterproofing/tiling after 3 days. This system was also used to repair the Jacuzzi’s surrounding walls prior to waterproofing, tiling, and grouting.


Sopro RAM 3 levelled the deck area (3-60mm) between the drainage channel edge and pool perimeter movement joint. Sopro RAM 3 was bonded with Sopro GD 749.


No featured products in this case study

Contact SMET Building Products Ltd by clicking the button below to find out which products were used in this case study.

More case studies from SMET Building Products Ltd

View all case studies (42)
44,000 m2 of Screed delivered to our partners for The National Forensic Mental Health Hospital in Portrane, Ireland

44,000 m2 of Screed delivered to our partners for The National Forensic Mental Health Hospital in Portrane, Ireland

LiteFlo® Lightweight Flowing Screed | Fast Floor Screed | First Floor Timber frame

LiteFlo® Lightweight Flowing Screed | Fast Floor Screed | First Floor Timber frame

LiteFlo® Lightweight Flowing Screed | Floor Screed Ireland | Our Lady of Hope School Crumlin

LiteFlo® Lightweight Flowing Screed | Floor Screed Ireland | Our Lady of Hope School Crumlin

14,000 m2 LiteFlo® Lightweight Flowing Screed | The Tower at GWQ London

14,000 m2 LiteFlo® Lightweight Flowing Screed | The Tower at GWQ London