OVERVIEW
Burton Green Primary School is located in the historic city of York, an outstanding school at the heart of a local community this primary school strives for excellence. The challenging and nurturing learning environment allows children to learn and grow, while achieving the highest potential possible in all areas of the 21st century curriculum.
When the roof began showing signs of ageing, it was clear that a long-term solution was required. Working with Project Managers Charles Garth and Principal Contractor Castle Special Projects, Polyroof would work towards providing the best solution to refurbish the ageing roof.
The work required and condition of the roof needed to be established first, to do this a survey was scheduled to take place. The survey was conducted on roofing area and it was determined that there were 6 flat roofs that required refurbishment. Areas 1 to 2 were constructed of a built up felt with mineral cap sheet, 50mm PUR insulation, bituminous vapour control, asphalt, 12mm fibreboard and a 50mm woodwood slab deck with timber joists. Areas 3 to 5 were constructed of a built up felt with mineral cap sheet, 50mm Jablite insulation, bituminous vapour control, asphalt, 12mm fibreboard and a 50mm wood wool slab deck with timber joists. Roof area 6 was made up of built-up felt with mineral cap, plywood and timber joist. The original build-up of roofs 1 to 5 needed to be stripped back to the asphalt due to the aged condition of the built-up felt, numerous leak reports were reported. Roof 6 and its original waterproofing was to be retained and made good, later this surface would act as the substrate for the new waterproofing system.
Once the survey was completed, a bespoke specification was written and it was recommended that the roofing areas would all benefit from a high-performance waterproofing system. In addition to this it was specified that the roof would be thermally upgraded to reduce the risk of condensation and provide lower fuel bills and energy consumption for Primary School further adding benefits to making improvements to the roof.
Liquid Roofing Limited an experienced roofing contractor and Polyroof Approved Contractor was chosen to undertake the work to this project. The proposed system for this project would be Polyroof Protec Warm Roof System. Protec’s liquid roof membrane has a unique flexible hybrid polymer formulation and can be applied to virtually all common roof surfaces.
The areas that were required for installation firstly needed to be stripped and removed back to the asphalt, areas 1 to 5 required this. Area 6 was then repaired of any defects and made good where necessary. All roofs required a deep clean, removing any dirt or debris that remained from the first stage. Once this preparation was completed an Air & Vapour Control Layer (AVCL) was then installed to roof areas 1 to 5 making sure that all surfaces are smooth and without voids.
Using a Polyroof Twin Pack Insulation Adhesive the Polyroof RES insulation (T&G) boards were bonded and laid to each of the 6 roof areas completing the second stage of the warm roof upgrade. Before the last stage of the installation could begin all joints in the insulation were sealed using taping matt and Polyroof Protec Resin. Polyroof’s extra-tough GRP trims were then installed to create neat and robust edge detailing for exposed perimeters before the main Protec system application commenced.
During the project there were some challenging aspects that required care and attention. The project featured a large array of different details ranging from installation of new substrates and trims for parapet walls to the removal of and preservation of tiles/cladding so that the Protec system could be applied correctly. These features required delicate work so that the original tiles/cladding could be reinstated after the application of the system was completed. During the project the rooflight that was originally in place was removed and replaced with a new, before this could happen the Protec system was taken up the upstands and then sealed under flange.
Once the project was completed within the relevant time frame of the client and within the budget specified, the Polyroof Technical Services team conducted a detailed inspection showing a high level of workmanship which lead to the client gaining the trusted Polyroof Accredited System Guarantee.
Protec Warm Roof Systems - Cold-Applied Liquid Membrane
Protec Overlay Roof Systems - Cold-Applied Liquid Waterproofing
Fleming Park Leisure Centre
Durham University Gateway
Barton Hill Academy
Blackfordby St Margaret’s Primary School
Fleming Park Leisure Centre
Durham University Gateway
Barton Hill Academy
Blackfordby St Margaret’s Primary School
Fleming Park Leisure Centre
Barton Hill Academy
Blackfordby St Margaret’s Primary School
Beckfoot Allerton Primary School