NBS Source
I'm a manufacturer

Degafloor QTA / Full Broadcast - Swimming Pool Area Resin Flooring

OVERVIEW

A Degafloor Approved Installer - The National Flooring Company Ltd were approached by a A 4-star hotel, in the South of England, who had decided to update their flooring system around the swimming pool. The existing floor tiles, which had started to debond posed a trip hazard and therefore needed to be replaced. The client also advised they were experiencing problems with standing water.

Following the removal of the existing floor tiles, the installation of a new screed was required to build back the levels and ensure there were adequate falls in the floor for water to run back into the pool.


Throughout the installation, the gym remained open, and it had been advised that the pool closure needed to be kept to an absolute minimum. The National Flooring Company installed the Degafloor Deep Fill Mortar Repair system, a fast-curing underlayment, which ensured the refurbishment programme could continue with no downtime due to curing.


The existing drain was removed and replaced, along with the light box and leveller covers, which all received new stainless-steel units. A new trim was fixed around the perimeter of the pool and the Degafloor resin system, which has an excellent bond to metal surfaces, was abutted up to all the stainless-steel items.

The Degafloor QTA system used within the project, is a quartz trowelled system that can be laid to falls. The system is broadcast with aggregate to provide an extremely slip resistant finish, even under wet conditions, making it ideally suited to a swimming pool surround. Coved skirting was installed around the perimeter of the room creating a completely impervious finish, with no weak spots and therefore reducing future maintenance costs.


The full refurbishment was completed over 12 days, ensuring that the closure was kept to a bare minimum.

The clients main requirements were they required an anti-slip floor that would eliminate the current situation they had with standing water. They specifically requested that the closure was kept to a minimum as they are a "member's club" as well as facilitating the hotel, which remained open throughout the installation.

The client was extremely satisfied with the end result and felt they now have a floor finish that is much better suited to their environment.

Products featured in this case study

View all products (12)
Degafloor QT System and Aggregate - resin flooring - Resin Flooring

Degafloor QT System and Aggregate - resin flooring - Resin Flooring

Degafloor Full Broadcast - resin flooring  - Resin Flooring

Degafloor Full Broadcast - resin flooring - Resin Flooring

More inspiration from Degafloor Ltd

View inspiration
Degafill Pot Hole Repair - HAPAS - Resin

Degafill Pot Hole Repair - HAPAS - Resin

Degaflex Fire Rated Roofing System - Case Study - Resin

Degaflex Fire Rated Roofing System - Case Study - Resin

Degafloor Quartz Trowelled Aggregate - Long Clawson Dairy Resin Flooring

Degafloor Quartz Trowelled Aggregate - Long Clawson Dairy Resin Flooring

Degafloor QTA System - Swimming Pool Surround & Changing Rooms -Resin Flooring

Degafloor QTA System - Swimming Pool Surround & Changing Rooms -Resin Flooring

More inspiration from Resin flooring systems

View inspiration
ROUNDHOUSE TRUST, CAMDEN, LONDON

ROUNDHOUSE TRUST, CAMDEN, LONDON

WAGWORKS, FULHAM, LONDON

WAGWORKS, FULHAM, LONDON

CEDARWOOD HOUSE, BATH

CEDARWOOD HOUSE, BATH

GREAT ORMOND STREET HOSPITAL – Zayed Centre for Research into Rare Disease in Children - London

GREAT ORMOND STREET HOSPITAL – Zayed Centre for Research into Rare Disease in Children - London