Verified by manufacturer 7 days ago
EPD
Certificate type
BRE Certificate
Certificate type
Standing seam zinc roofing.
Suitable for buildings in 1 to 4 humidity classes (dwellings with high occupancy, sport halls, etc) with pitches from 3° to the vertical (as well as soffits).
Vented cold roof system for buildings with humidity classes between 1 and 4 using VMZINC on an open gap softwood boarding (compatible) substrate.
A minimum 50 mm continuous air gap must be left clear beneath the roof boarding. Continuous ventilation openings are made at the ridge and eaves. In order to maintain the integrity of the roof, a VMZINC breather membrane should be installed on the cold side of the insulation, and a vapour control layer appropriate to the building’s humidity levels laid on the warm side of the insulation.
VMZINC must be installed directly over the open-gap softwood boarding without the use of any membrane. The boarding should be clean and dry, 100–150 mm wide, 18 or 24 mm thick, according to the rafter centres.
The roof boards are fixed perpendicularly to the direction of the pitch leaving a 3–5 mm gap between them. They are securely fixed to the structure.
Features and benefits:
System build-up:
Life Cycle Analysis (LCA):
VMZINC undertakes Life Cycle Analysis (LCA) tests on its products and publishes Environmental Product Declarations (EPDs), such as BRE Environmental Profiles. These provide users with comprehensive, reliable and transparent information on relevant environmental characteristics. The information is also used by VMZINC as the basis for its eco-design approach.
Color | Blue Green Grey Red Brown |
Finish | Natural Pre-treated |
Material | Zinc |
Shape | Rectangle |
Length | 13000 mm Guidance for specification option: Max. |
Width | 430 mm 530 mm 600 mm |
Height | 25 mm |
Warranty description | 50 year Guidance for specification option: Up to 50 year material warranty available on a project basis. |
Uniclass | |
CAWS | H74/5 Zinc sheet fully supported covering to dormers H74/150 Zinc sheet fully supported covering to dormers H74/110 Zinc sheet fully supported roof covering |
Product range |
System performance | Structural performance – wind actionsDesign of zinc sheet fully supported roof covering systemsDurabilityAesthetic performanceFire performance |
Sarking or roof boarding | 18 mm open gap softwood boards.Guidance for specification option: With 50 mm minimum vented cavity, 10 mm open air inlet at the eave and 10 mm open air outlet at the ridge. 50 mm cavity created with a batten. |
Membrane | VMZINC Membrane.Guidance for specification option: Placed over insulation, VMZINC applied directly over open gap softwood boards. |
Insulation | As required. |
Air and vapour control layer | Guidance for specification option: A VCL is recommended and should be installed on the warm side of the insulation. |
Carrier | Batten (Rafters can be metal or timber). |
Sheet underlay | |
Fasteners | Screws as required. |
Timber cores for batten roll joints | |
Fasteners to substrate | Stainless steel fixed and stainless steel sliding clips. |
Zinc | Zinc-titanium-copper. |
Longitudinal joints | |
Form | Standing seam joints. |
Fixing standing seam joints | VMZINC clips, 1.4301 (304) stainless steel. The thickness of the fixing clip is 0.5 mm. The sliding clips have a moving component, which is 0.4 mm thick, and a 70 mm long slot. |
Fasteners to substrate | It is recommended that screws be used to secure the clips with three being used per sliding clip. The use of nails offers significantly less resistance, but in the event of using nails, contractors are advised to use ring shank nails. |
Cross joints | |
Form | Double lock welts.Roof steps. |
Eave details | |
Form | Dog tooth.Swept eave on T plate with water check. |
Fixings | Fixed with cleats using a 6 mm rebate on the substrate. |
Verge details | |
Form | Standing seam verge. |
Fixing | |
Top edge | VMZINC stainless steel sliding clip. |
Bottom edge | The eave should be fixed to a T plate with water check which must be secured using cleats. |
Ridge and hip details | |
Form | G3 ridge.Traditional with upstand. |
Fixings | Ridge clip G3. |
Samples required | Product samples |
Execution | Layout and zinc work generally. |
System completion | Submittals (e.g. operation and maintenance manuals). |
Finishes | Pre-weathered. Natural. Guidance for specification option: Only available with Natural colour option. |
Standard | EN 15804, ISO 14001 and ISO 9001. |
Coil | 0.7 x 500 mm. 0.7 x 600 mm. 0.7 x 670 mm. Guidance for specification option: Not AZENGAR. 0.8 x 500 mm. 0.8 x 600 mm. Manufacturer guidanceCoil thickness x coil width. Non-standard widths between 60–600 mm can also be produced. |
Centres | 430 mm. 530 mm. 600 mm. Guidance for specification option: Not AZENGAR. Manufacturer guidanceStanding seam centres. |
Panel weight | 6 kg/m² (approximately). |
Fire performance: | Fire classification A1 (Natural Zinc, QUARTZ ZINC, ANTHRA-ZINC and AZENGAR) and A2-s1,d0 (PIGMENTO and VMZINC PLUS) according to EN 13501-1:2002. |
Colour | Natural VMZINC®. Guidance for specification option: Only available with Natural finish option. Natural VMZINC has a shiny metallic appearance when new and develops a patina over time. In facade applications, it may take 10 years for the matt grey patina to form. It can be quickly soldered without removing the patina. Standard PIGMENTO® BLUE. Standard PIGMENTO® GREEN. Standard PIGMENTO® BROWN. Standard PIGMENTO® RED. |
Contains Red List materials | No |
Country of material origin | France |
Country of product manufacture | France |
Material | Zinc |
Embodied carbonA1-A3 (production stage) as defined in BS EN 15804 | Manufacturer guidanceSee EN15804 EPD. |
Recyclability | 100% Guidance for specification option: Fully recyclable. |
Recycled contentAs defined in clause 7.8 of BS EN ISO 14021 | 20 % Guidance for specification option: 20% (approximately). |
Expected Life | 100 year |
NBS BIM Object Standard
This BIM object has been authored to meet the requirements of the NBS BIM Object Standard.
Find out more about the NBS BIM Object Standard.
Platform | Compatible | Version |
---|---|---|
IFC2X3 | 1 | |
Revit 2016 | 2 |
VMZINC Standing Seam Installation Guide - Information about the Use and Detailing of VMZINC March 2018
VMZINC Roofing + Rainwater Design Specification & Installation Guidelines Dec 20
VMZINC General Technical Recommendations - Design Guidance for Architects & Contractors.
VMZINC EN15804 Natural Rolled Zinc
ISO 9001
ISO 14001
EN15804 Pre-Weathered QUARTZ PLUS & ANTHRA PLUS
BRE Certification EN15804 Pre-Weathered Rolled QUARTZ & ANTHRA
BRE Certification EN15804 Pre-Weathered PIGMENTO & STRAT
VMZINC Standing Seam Roofing - Compact Roof (Warm, Non-vented)
VMZINC Standing Seam Roofing - Standing Seam Roof On Metal Faced Panels (Warm, Non-vented)
VMZINC Standing Seam Roofing - Standing Seam Roof On Plywood (Cold, Vented)
VMZINC Standing Seam Roofing - Standing Seam Roof On Plywood Bonded To Phenolic Foam (Warm, Non-vented)
VMZINC Standing Seam Roofing - Structural Roof (Warm, Non-vented)