The extension provides eight new classrooms to develop the college’s specialism in teaching the sciences to 11-16 year-olds. The first phase to create five classrooms over a 700m2 floorspace was completed within 37 weeks by the Christmas holiday of 2008. The second phase to create three classrooms over a 450m2 floorspace was completed within 27 weeks by the start of the summer holiday. The fittings and furnishings are installed during the holidays.