This case study is no longer available
The project to install the 108 foundations, including the grouting works, took just 5 months to complete, averaging 21 foundation installations per month. A world record in the industry, and a new benchmark for future offshore windfarms. Over 4,770 tons of MasterFlow 9500 Exagrout was pumped into the monopile transition piece connections on this project. Because of the early strength development of MasterFlow 9500, the permitted weather window, which is necessary for the installation operation,…
Show moreContact Master Builders Solutions UK Ltd by clicking the button below to find out which products were used in this case study.