This former warehouse which is Grade II listed has had a 6 million pound revamp into prestigious offices in the centre of Manchester.
Employed by ARJ Construction to undertake the refurbishment of the sash and casement windows, the works comprised of:
Overhaul
Draught Exclusion
Timber Repair using the Repaircare System
Contract Details
Client: ARJ Construction
Contract Period: June 2013 – February 2014
Contract Value: £108k