Flue Relining for Gas Boilers – FuranFlex Case Studies

by Kompozit'All UK

  Favourite

Initial Situation: The 25-metre flue at the Isle of Wight council offices serviced 2x large commercial condensing boilers. The flue was leaking badly through the chimney walls due to condensate caused by the boilers. Project Challenge: Reconstructing the flue Liner Chosen: FuranFlex 25 Black Result: 3 metres had to be reconstructed to the chimney and a 28m x 450mm FuranFlex 25 Black was installed. New stainless steel pipework was installed from the boilers to the FuranFlex which now has a suitable valve for collecting and draining the condensate. Installer: Toast (Southern) Ltd.