The Shard

OVERVIEW

The Challenge was To pump screed 47 floors up in a ‘single pump’ operation. And to lay 1800m2 a day for the Shangri La Hotel section of The Shard. 40mm Gyvlon SKY on a resilient layer to part E, pumped internally in the building to allow the glass cladding and other operations to continue. Single pump operation at 14m3 per hour up 200 metres

No featured products in this case study

Contact Anhydritec Ltd by clicking the button below to find out which products were used in this case study.