OVERVIEW
In 2013, when Cemfree was still in its infancy, DBG decided to pour the first ever in-situ Cemfree slab. Although the slab was large, measuring 930m2, the real challenge lay in pouring the Cemfree mix in temperatures of -2°C; far from ideal conditions for placing concrete. As well as contending with below-freezing conditions, DBG wanted to lay the slab in one continuous pour with no joints, a practice that would not normally be recommended for traditional concrete slabs of this size, due to the increased risk of cracking.